Latest topics
» PhilGEPS Issuance of Certificate of Registration for New Suppliers
Today at 3:55 pm by vicong_grandcorp

» BIDBULLETIN
Yesterday at 9:15 am by zeph03

» QUERY ABOUT PHILGEPS PENDING TASK
Yesterday at 9:14 am by zeph03

» Additional Member of TWG
Thu May 24, 2018 5:26 pm by Gracy0527

» Postponement of a Schedule Bidding
Thu May 24, 2018 10:35 am by alvsvb6

» Post in PhilGEPS
Thu May 24, 2018 10:21 am by richel2015

» WITNESS for the Procuring Entity in the Contraxt Agreement
Tue May 22, 2018 8:26 pm by amilan2018

» forgotten password of email address
Tue May 22, 2018 4:56 pm by leafranee

» PUBLIC AUCTION
Tue May 22, 2018 8:14 am by ford15

» PARTIAL PAYMENT OF WORKS UNDER SMALL VALUE PROCUREMENT
Thu May 17, 2018 4:50 pm by amilan2018


Partial Acceptance of Award after Bid Validity Period

Go down

Partial Acceptance of Award after Bid Validity Period

Post by Dave Jubilado on Tue Oct 27, 2015 11:06 am

Good day.
Our Agency conducted a bidding for construction materials sometime in March 2015, however the award was made only in July due to the delay in the releasing of our SAA from the DBM. The supplier informed us in writing that he can no longer accept the award since his bid offer is no longer valid. However, he expressed his willingness to still accept the award for all other items except for one (cement) due to price escalation. In the exigency of the service, can we still issue the award for all other items except for cement and conduct a re-bidding for that item alone, or should we go to through the process of public bidding again for all the items being procured?



Dave Jubilado
New Member
New Member

Male Number of posts : 2
Company/Agency : National Irrigation Administration R.O. IX
Occupation/Designation : Chief Corporate Accountant B
Registration date : 2015-10-22