Latest topics
» Post Qualification
Yesterday at 7:55 pm by siddecruz

» Acquisition RROW
Yesterday at 7:54 pm by siddecruz

» Cancellation of Notice to Proceed
Fri Jul 13, 2018 11:10 pm by Lumi

» retrieve of user ID and password
Thu Jul 12, 2018 12:45 pm by johnrayconcreteproducts

» Conduct of Post Qualification
Wed Jul 11, 2018 4:45 pm by ford15

» Can we consider the composition of the BAC as valid if one of the members refuses to perform function as BAC member?
Wed Jul 11, 2018 10:57 am by rubyrose

»  Locked PhilGEPS
Tue Jul 10, 2018 11:53 am by eumarmahal

» RE: INVITATION TO BID
Tue Jul 10, 2018 11:32 am by irishpugong

» Request for review of uploaded documents for platinum renewal
Tue Jul 10, 2018 10:27 am by zcabarios

» Platinum Membership Renewal?????
Tue Jul 10, 2018 10:23 am by zcabarios


REVISION OF PPMP

Go down

REVISION OF PPMP

Post by shark on Thu Mar 07, 2013 2:45 pm

need help on these matter:

SCENARIO 1:
A PPMP submitted by the end-user is composed of , say, 10 projects. List of projects in the PPMP was consolidated in the APP. After the approval of the APP, the end-user submitted another PPMP revising the schedule of activity of one of the projects listed in the previous PPMP.

- do we need have to assign another PPMP number and make another APP for the revised item (project) which is part of the previous PPMP and approved APP?


SCENARIO 2:
A PPMP for "project A" submitted by the end-user was consolidated in the APP. After the approval of the APP, the end-user submitted another PPMP revising the estimated budget reflected in the previous PPMP for "project A".

- is it allowed to revise the PPMP or should the previous be PPMP be cancelled?

avatar
shark
New Member
New Member

Female Number of posts : 43
Company/Agency : LGU
Occupation/Designation : sekretarya_lang
Registration date : 2009-10-29

Back to top Go down

Re: REVISION OF PPMP

Post by RDV @ GP3i on Fri Mar 08, 2013 9:51 am

shark wrote:need help on these matter:

SCENARIO 1:
A PPMP submitted by the end-user is composed of , say, 10 projects. List of projects in the PPMP was consolidated in the APP. After the approval of the APP, the end-user submitted another PPMP revising the schedule of activity of one of the projects listed in the previous PPMP.

- do we need have to assign another PPMP number and make another APP for the revised item (project) which is part of the previous PPMP and approved APP?

First of all, a PPMP should be prepared on a per project basis only. Therefore, it should not contain more than one project.

If thre is a revision in the PPMP, the APP should be revised also, but you may just have to schedule the revision, when already necessary. You need not revise the APP every time you receive a revised PPMP.


shark wrote:SCENARIO 2:
A PPMP for "project A" submitted by the end-user was consolidated in the APP. After the approval of the APP, the end-user submitted another PPMP revising the estimated budget reflected in the previous PPMP for "project A".

- is it allowed to revise the PPMP or should the previous be PPMP be cancelled?


A revision of PPMP is the proper way to do.
avatar
RDV @ GP3i
Grand Master
Grand Master

Male Number of posts : 1611
Company/Agency : DBM-Reg'l Office IV-B
Occupation/Designation : Regional Director/ Procurement Trainer
Registration date : 2008-09-04

http://gppphil.org/

Back to top Go down

Re: REVISION OF PPMP

Post by shark on Mon Mar 11, 2013 4:43 pm

thank you sir RDV! Smile
avatar
shark
New Member
New Member

Female Number of posts : 43
Company/Agency : LGU
Occupation/Designation : sekretarya_lang
Registration date : 2009-10-29

Back to top Go down

Re: REVISION OF PPMP

Post by Sponsored content


Sponsored content


Back to top Go down

Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum